Hi All - I am new to this forum so please take it easy on me :)

I have many scheduled reports running on my Cognos server, but would like to have more than one report run at once. So for example at 9am 3 reports run and complete, then assuming the 3 have finished I can have 3 more scheduled to run at 9.10am
I can't seem to get reports running concurrently - can anyone please help
Thanks in advance!

navissar

I'm not sure I understand, so correct me if I'm wrong: You want several reports to run together at the same time? That's easy, put them in a job and set the job to run concurrently. However, note that the maximum reports Cognos can run in parallel is as set in the Dispatcher settings.