Why does my ReportNet return 48 when given

_week_of_year(current_date)

and current date is today, 2005-11-21.

According to function tips this should be week 47 but as stated I get 48 in return. How does it bust up weeks?

Thanks,

Bob

zenith

I did try the same function and it returns me week 47
Had you checked the system date before you ran the report
Maybe that could be the factor

rlcaputo

Yes I have,  _week_of_year(2005-11-21) also returns 48.

And as I mentioned current date was correct.

I have done several test with hardcoded dates for inputs and it seems there is a week 53 last year and no week 1 this year.

??????

Is this settable somewhere in the ReportNet setup?

sir_jeroen

It depends on where you live... USA has other weeknumbering that eg EU

rlcaputo

I am in Wisconsin which last I knew was in US.

Bob

sir_jeroen

#5
Oh... you can't help that.. :P
But if you look in a paper agenda... what does the week# say?
And what's your first day of week?
The week# is calculated according to ISO-8601. Perhaps you should have a look into that standard...

rlcaputo

Yes its probably one of those standards issues. I believe Cognos is returning week-of-year vs fiscal-week. Depending on your definitions that may be two different numbers.

Case closed, thank you,