I am need of estimation effort for FM modeling in simple,medium,complex models, and how we can catogries as simple,medium &complex model when we have only RFP and ask to estimate.
And same for reports too.
Thanks in advance
K.M
In general (service companies) we have some standards for cognos reports that should follow in every
project
Not for only FM; from report design phase to testing this is the time frame(excluded specification document preparation time)
Simple: 5 Days*
Medium: 7 Days*
Complex: 10 Days*
*Including buffer
Generally the Simple,Medium and Complex are calculated by seeing into the report layout, design challenges, calculation etc.,