COGNOiSe.com - The IBM Cognos Community

IBM Cognos 8 Platform => COGNOS 8 => COGNOS 8 Administration => Topic started by: beerguy82 on 28 Apr 2009 02:03:36 PM

Title: Schedule of Scheduled Reports
Post by: beerguy82 on 28 Apr 2009 02:03:36 PM
Is there any way to extract when the next scheduled occurrence of a scheduled report is supposed to run?  We are looking to change how often we build our cubes in a week and want to disrupt as few schedules as possible.  Thanks.

Tim
Title: Re: Schedule of Scheduled Reports
Post by: mikewalker on 29 Apr 2009 09:01:59 AM
That information should be under the Server Administration area in Cognos Connection.

Click Tools > Server Administration > Schedule

HTH
Title: Re: Schedule of Scheduled Reports
Post by: gppande on 07 May 2009 08:41:58 AM
In CRN, you have an option to see future schedules on the schedule management page