IBM Cognos 10 Platform => Cognos 10 BI => Event Studio => Topic started by: Dev1975 on 16 Nov 2016 03:23:38 AM

Title: Use EventStudio to monitor completion of schedule
Post by: Dev1975 on 16 Nov 2016 03:23:38 AM
Hi everyone,

I've got a requirement to setup an EventStudio agent that monitors a Planning Macro job and sends an e-mail out when the job completes. I have setup an agent that runs a few minutes after the job finishes and monitors the Audit database for the job name and the status of "Success" but that isn't ideal, as it's scheduled to run at a set time, not when the job completes, which could be any time.

How would I go about amending the agent so that it ONLY runs once the Planning Macro job has completed? What should I be monitoring to ensure this happens?

TIA!
Dev
Title: Re: Use EventStudio to monitor completion of schedule
Post by: Dev1975 on 30 Jan 2017 01:47:18 AM
Hi everyone,

So I've currently got an EventStudio agent setup that sends out an e-mail when a Planning Macro runs, which is all good. However, is there a way of updating it so that it sends out an e-mail if the macro has been running for (e.g.) an hour without completing? Is there a particular entry that I should be monitoring in the Audit package (or elsewhere) that would be able to do this?

Cheers,
Dev