I haven't been in touch with Report Studio for quite some time so pardon me if this is an easy one.
I have a report with one prompt for Entity Code and I want to send the report to Executives via E-Mail.
So there are two EMail groups, one for each Entity. I set up a schedule and selected one Entity Code
from the Prompt while setting up the schedule but then there is no option to create another schedule !
So how do I schedule the report to select another value from the Entity Code so that the next output
can be sent to the 2nd EMail group ?
I did a search and found a post which says that Event Studio can be used for this . I did try but can't
understand how a parameter value from Event Studio can be passed to the report !
Any help will be appreciated.
how about you create two report views? one for each entity code, then schedule them accordingly?
Excellent ! Thanks so much !