IBM Cognos 8 Platform => COGNOS 8 => Report Studio => Topic started by: ankit.agg.2008 on 31 Jul 2013 05:40:56 AM

Title: Drill Through Capability on the slices of Pie Charts
Post by: ankit.agg.2008 on 31 Jul 2013 05:40:56 AM
Hi everyone,

I have a question regarding the 'drill behavior' capabilities in a pie chart.


Is it possible to drill into a slice and the pie chart changes to only show the child componets of the slice (i.e. if there were 2 child components of a slice, the revised pie would only show the 2 child components of the selected slice when drilled into). If so, could you please advise of any settings or conditions which need to be set to allow this functionality to work.

Thanks.
Title: Re: Drill Through Capability on the slices of Pie Charts
Post by: MFGF on 31 Jul 2013 09:38:27 AM
Hi,

This is default behaviour when drilling down in a pie chart. The chart re-renders to show slices for the children of the member represented by the slice you drill on.

Just go to Data > Drill Behavior and enable drill up and down.