Drill through from Cube to relational report

Started by redmist, 23 Sep 2009 05:50:31 PM

Previous topic - Next topic

redmist

Hi,

I started off trying to create a drill through report from a cube based on 2 dimensions (Time and Product). I kept getting error which on further investigation revealed that only one of the parameters was getting passed properly to the report.
From the View Target Mapping option, i could see that the date values were not getting carried over properly.

The Use value column shows the following
009-09-0 00:00:00.000
009-09-3 23:59:59.999

It should infact have been
2009-09-01 00:00:00.000
2009-09-30 23:59:59.999

but the first number of the year and last number of the day is being truncated. Have any of you come across a similar issue.
I tried all options under 'Source Metadata item properties'


PS: my version is 8.4 GA


kaevne

try creating an extra data item where you cast it to a date and use that instead.

redmist

kaevne,

the dataitem in the relational report is infact a date field. Does it matter that it is not a datetime field?
Anyway I tried converting it to a datetime field too but that did not work either

sr71_mavericky

Hi Redmist,

Were you able to resolve this issue?

I am having the same exact issue for 3 days and have been pulling my hair out ... tried all sorts of casts, to_date, to_char combinations, to no avail.

Any updates you have on this would be great!


thanks,
mavericky


redmist

sr71_mavericky

i do not have a solution for this. I'm going to open a SR with support.
Not too sure about this but I did read in another post in this forum that this is a bug in 8.4