We've had a report within a schedule set to run once week on every Saturday. On February 1 a Thursday it ran. According to the schedule it shouldn't have run until February 3 a Saturday. Today seven days later it appears to have run again, even though we had disable the scheduler. Is there any audit report that would show us what happen or why this happened?